

Turkish shipyard delayed delivery of your newbuild vessel? Learn how foreign buyers can claim liquidated damages, compensation, price reduction, cancellation, refund of instalments and other remedies for shipbuilding delays in Turkey.
A foreign shipping company signs a contract with a Turkish shipyard for construction of a new vessel. The contract specifies the technical characteristics, classification requirements, contract price, payment instalments and a fixed delivery date.
The buyer may already have arranged financing, entered into a long-term charter, contracted with cargo interests or planned fleet deployment based on that delivery date.
Then construction falls behind schedule.
The shipyard first announces a delay of several weeks. The delivery date is extended again. Sea trials are postponed. Classification work remains incomplete. Eventually, a vessel expected in March may still be under construction months later.
For the foreign buyer, the financial consequences can be enormous.
The central questions become:
Can the buyer claim compensation for every day of delay? Can the contract price be reduced? When can the buyer cancel the shipbuilding contract? Can paid instalments be recovered? Can lost charter earnings be claimed? Does force majeure excuse the shipyard? What happens if the buyer has already accepted several extensions?
The answer begins with the shipbuilding contract itself. International shipbuilding contracts commonly distinguish between permissible and non-permissible delay, impose notice requirements on the builder, provide predetermined price reductions or liquidated damages for delay, and grant cancellation rights once delay passes a contractual threshold.
A vessel delivery date is not merely an administrative deadline.
Commercial deployment of the ship may depend on it.
A buyer may have arranged a five-year time charter beginning shortly after scheduled delivery. Financing repayments may commence. Crew may already have been recruited. Insurance may have been arranged. Another vessel may have been sold in anticipation of fleet replacement.
A three-month delay can therefore cause losses far exceeding the monthly construction instalment.
This is why sophisticated shipbuilding contracts usually contain detailed delay provisions.
The original delivery date should be established first.
Then determine whether that date has been validly extended.
The current contractual delivery date may differ significantly from the date originally written on the first page of the agreement because of approved modifications, buyer-supplied equipment delays, permissible delays or previous amendments.
The buyer should prepare a complete timeline showing:
Original Delivery Date → Claimed Extensions → Buyer Objections → Revised Delivery Date → Actual Project Status.
This timeline often becomes the foundation of the entire claim.
This distinction is fundamental in shipbuilding disputes.
A permissible delay generally gives the builder a contractual extension of the delivery date without triggering the same financial consequences as a delay attributable to the builder.
A non-permissible delay generally counts against the builder and can trigger contractual price reductions, liquidated damages or eventual cancellation rights.
The terminology varies between contracts.
The contractual definitions therefore control.
Shipbuilding contracts frequently identify events such as extraordinary weather, government restrictions, war, certain strikes, earthquakes, fires, embargoes, supply interruptions and specified classification-related events.
But the mere occurrence of an event does not necessarily justify every day of delay claimed by the yard.
Shipbuilding delay analysis commonly requires the builder to establish a causal connection between the qualifying event and actual delay to vessel completion. Industry analysis also emphasizes the importance of mitigation and demonstrating that the event affected the construction schedule. (DergiPark)
Suppose the shipyard says:
“Equipment arrived late from our supplier, so we claim a 90-day extension.”
That statement alone should not end the analysis.
The buyer should ask:
Was the equipment ordered on time?
Could another supplier reasonably have been used?
Was the equipment actually on the project’s critical path?
Was the vessel already delayed for unrelated reasons?
Did the yard take reasonable steps to minimize the delay?
The builder should not automatically receive an extension merely because some difficulty occurred during construction.
This is one of the most important contractual protections for foreign buyers.
Shipbuilding contracts commonly require the builder to notify the buyer promptly after a delay event begins and later provide details concerning the duration of the claimed extension. Publicly filed shipbuilding contracts illustrate notice periods as short as seven or ten days and may expressly attach consequences to failure to comply.
The precise contract must therefore be checked.
The buyer must also act carefully.
Some contracts provide that failure to object to a claimed extension within a specified period can prejudice the buyer’s ability to challenge it.
For example, publicly available shipbuilding contracts contain mechanisms under which failure to respond within a short contractual period can constitute waiver of the right to object to an extension.
A foreign buyer should therefore never leave delay notices unanswered.
If the buyer disputes the claimed extension, the objection should be made clearly and within the contractual period.
The response should identify why the buyer rejects the delay.
For example:
the event was not contractually permissible,
the event did not cause the claimed delay,
the yard was already behind schedule,
notice was late,
or the yard failed to mitigate.
The buyer should expressly reserve all contractual rights.
Many shipbuilding contracts establish predetermined financial consequences for non-permissible delay.
These may be structured as a reduction in the contract price or as liquidated damages calculated according to the number of days or weeks of delay.
For example, the contract may provide that after an initial grace period, the price is reduced by a specified amount for each day of delay.
The exact formula can vary considerably.
Without a predetermined formula, the buyer may need to prove its actual loss in detail.
A contractual delay formula can simplify the claim.
Turkish-law commentary on shipbuilding contracts recognizes that contractual liquidated-damages or penalty provisions for late delivery can be binding between the parties, subject to the applicable legal framework. (Lexology)
Foreign buyers should therefore calculate the contractual delay amount from the first day it becomes payable.
This question becomes particularly important where both parties are commercial enterprises.
Turkish Commercial Code rules concerning penalties between merchants can significantly restrict attempts to reduce contractual penalty amounts merely because they are high. Turkish shipbuilding-law commentary notes the importance of TCC Article 22 in this context, while recognizing exceptional circumstances considered by Turkish courts. (Lexology)
The precise characterization of the contractual clause must nevertheless be examined carefully.
Potentially, but this depends heavily on the contract and applicable law.
The agreement may state that liquidated damages constitute the buyer’s sole and exclusive remedy for delay up to the cancellation threshold.
Alternatively, the contract may leave room for additional damages in specified circumstances.
Never assume that a substantial actual loss automatically permits recovery above the contractual delay formula.
The wording must be reviewed.
One of the largest potential losses involves a charter arranged for the new vessel.
Suppose a foreign buyer has agreed to take delivery of a new tanker in June.
A five-year charter begins in July at USD 45,000 per day.
The shipyard does not deliver until October.
The buyer may lose several months of charter revenue or potentially the entire fixture.
Whether those losses are recoverable depends on the contract, applicable law, foreseeability, causation and any exclusion of consequential loss.
If the buyer intends to claim lost charter earnings, preserve:
the signed charterparty,
fixture recap,
broker communications,
daily hire rate,
cancellation provisions,
charterer’s termination notice,
and evidence connecting the loss directly to delayed vessel delivery.
A confirmed fixture provides significantly stronger evidence than a general statement that the vessel “could have been chartered.”
Delivery delay can also affect vessel financing.
The buyer may incur commitment fees, extension charges, hedging costs or financing restructuring expenses.
Whether these amounts can be recovered from the builder depends on contractual liability provisions and applicable damages rules.
Detailed banking evidence should be preserved.
A buyer may need to charter a substitute vessel because the newbuild is unavailable.
For example, the buyer expected to deploy its new vessel under an existing transportation commitment but must instead charter another vessel at a substantially higher market rate.
The additional cost may potentially form part of the buyer’s claimed loss, subject again to contractual limitations and general damages principles.
Shipbuilding contracts frequently establish an ultimate delay threshold after which the buyer may cancel or rescind.
The precise threshold varies.
Publicly available contracts illustrate cancellation mechanisms triggered after accumulated delay reaches contractually specified periods such as 180, 210, 240 or more days depending on the structure of permissible and non-permissible delays.
There is therefore no universal “180-day rule” applicable to every Turkish newbuild.
Read the contract.
Cancellation of a multimillion-dollar shipbuilding contract should never be done casually.
The buyer must confirm:
the correct cancellation threshold,
how permissible delay is counted,
how non-permissible delay is counted,
whether any exclusions apply,
whether notice requirements were satisfied,
and exactly how cancellation must be communicated.
An invalid cancellation could expose the buyer itself to a substantial breach claim.
Where Turkish law governs the shipbuilding relationship, general rules of the Turkish Code of Obligations may also become important.
Turkish shipbuilding commentary notes that Article 473 of the Turkish Code of Obligations can permit a customer to rescind before the delivery date where, because of the contractor’s delay in commencing or progressing the work and without fault of the customer, it becomes clear that timely completion is no longer possible. (Lexology)
This can become significant where the vessel is obviously nowhere near completion even though the contractual delivery date has not technically arrived.
Not necessarily in every Turkish-law case.
Imagine the contract requires delivery in three months.
The vessel should be nearly complete.
Instead, major construction stages have not begun and technical evidence demonstrates that completion within three months is impossible.
Depending on the contractual structure and applicable Turkish obligations law, the buyer may need to examine whether early remedies are available rather than waiting passively for an inevitable default. (Lexology)
Turkish-law analysis of shipbuilding contracts also identifies general default remedies under the Turkish Code of Obligations.
Depending on the circumstances, a buyer faced with builder default may seek performance together with delay damages or pursue remedies based on non-performance or rescission subject to statutory and contractual requirements. (Lexology)
However, sophisticated shipbuilding contracts often modify and structure these remedies extensively.
The contract and governing law must therefore be analyzed together.
Newbuild vessels are usually paid through construction instalments.
By the time serious delay develops, the buyer may already have paid millions of dollars.
If the buyer validly cancels the contract, recovery of paid instalments becomes a central issue.
The contract should state what must be refunded, when repayment becomes due and whether interest is payable.
This is why a refund guarantee is one of the most important documents in a newbuild transaction.
The buyer may hold a bank-issued guarantee securing repayment of construction instalments if the builder becomes obliged to refund them under the shipbuilding contract.
When delay approaches the cancellation threshold, the refund guarantee should be reviewed immediately.
Do not wait until after cancellation.
This point can be critical.
The shipbuilding contract may be delayed for months while the refund guarantee approaches expiry.
The buyer should verify:
the guarantee amount,
issuing bank,
expiry date,
extension mechanism,
demand requirements,
governing law,
and required documents.
A cancellation right is much less valuable if the shipyard cannot repay the instalments and the guarantee has expired.
Persistent delay may indicate more than technical difficulty.
Warning signs can include unpaid subcontractors, work stoppages, difficulty obtaining equipment, demands for early instalments or repeated unexplained schedule changes.
Foreign buyers should investigate whether the yard is experiencing financial distress.
A construction-delay dispute can quickly become an insolvency problem.
Shipbuilding instalments are usually linked to construction milestones.
If the yard requests the next instalment, the buyer should verify that the contractual milestone has actually occurred and that any required certificate has been properly issued.
Paying ahead of actual construction progress increases exposure if the project later fails.
Classification documentation can provide valuable independent evidence of construction progress.
The buyer should review class surveys, approvals, outstanding items and technical reports.
If the shipyard claims the vessel is nearly ready but significant class requirements remain unresolved, those records can challenge the yard’s position.
Sea trials are a frequent source of final-stage disputes.
The vessel may appear almost complete but repeatedly fail scheduled tests.
Engine problems, speed deficiencies, fuel-consumption issues, vibration or equipment failures may prevent delivery.
A failed sea trial should be documented carefully.
Sometimes the dispute is not merely about late delivery.
The yard may offer delivery on time, but the vessel does not comply with contractual specifications.
The buyer should not allow a delay dispute to pressure it into accepting a defective ship.
Acceptance rights, rejection rights and outstanding defect mechanisms should be reviewed separately.
Newbuild contracts often guarantee speed, fuel consumption, deadweight, capacity and other technical characteristics.
Failure to satisfy these guarantees may trigger separate price adjustments or rejection rights.
These remedies can operate alongside delivery-delay provisions.
The buyer should therefore calculate each contractual claim separately.
The shipyard may argue that the foreign buyer itself caused the delay.
Common allegations include:
late design approvals,
late payment,
late delivery of buyer-supplied equipment,
excessive modifications,
or delayed technical decisions.
Public shipbuilding contracts commonly grant delivery-date extensions for specified buyer-caused delays.
The buyer should maintain detailed records showing when every required approval and item was provided.
Buyers frequently request changes after construction begins.
The yard may later use those modifications to justify extensive extensions.
Each variation should therefore specify:
technical scope,
additional price,
and extension of delivery date.
Avoid open-ended wording such as “delivery schedule to be adjusted accordingly.”
A particularly difficult situation arises when both sides contribute to delay.
Suppose the buyer delivers equipment 15 days late, but the yard was already 40 days behind schedule.
The yard may attempt to claim the entire period as buyer-caused delay.
Detailed construction scheduling and critical-path analysis may be required.
Maritime analysis of shipbuilding delay disputes recognizes concurrent delay and causation as important issues when determining whether buyer modifications genuinely caused late delivery. (DergiPark)
The foreign buyer should obtain and preserve:
baseline construction schedule,
updated schedules,
monthly progress reports,
critical-path reports,
yard correspondence,
subcontractor information,
class reports,
and photographs.
These records can establish whether a claimed force majeure event genuinely delayed the final delivery date.
High-value newbuild delay disputes frequently require naval architecture or project-management experts.
An expert may analyze the critical path and determine whether the shipyard’s alleged delay event actually affected completion.
For a vessel worth USD 50 million or USD 100 million, technical delay analysis can determine millions of dollars in liability.
The buyer’s site team can become a crucial evidentiary source.
Daily reports should document:
construction progress,
manpower,
missing equipment,
technical defects,
failed tests,
work stoppages,
and explanations provided by the yard.
Contemporaneous records are much stronger than recollections prepared after arbitration begins.
International newbuild contracts commonly provide for arbitration.
The forum may be Turkey or another agreed arbitral seat.
Before serving a cancellation or damages notice, counsel should review the arbitration clause, governing law and notice requirements.
Procedural mistakes can significantly weaken an otherwise strong commercial claim.
Where Turkish courts have jurisdiction, shipbuilding disputes can involve extensive technical expert examination.
Foreign buyers should prepare the case around a clear chronology rather than submitting thousands of pages of unstructured construction correspondence.
The central questions should remain:
What was the contractual delivery date?
Which extensions were valid?
How many days of non-permissible delay occurred?
What contractual remedy does that number trigger?
A foreign buyer contracts with a Turkish yard for a new bulk carrier.
Delivery is due on 1 June.
After evaluating valid extensions, the vessel is delivered 60 days late.
The contract provides a daily price reduction after a grace period.
The buyer should calculate the contractual reduction precisely and reserve its rights before final settlement and delivery documentation are signed.
A new tanker is due for delivery on 1 September.
The buyer has already signed a five-year charter beginning 15 September.
The yard is unable to deliver until December.
The charterer cancels.
The buyer should immediately preserve the charterparty, fixture correspondence, cancellation notice and evidence showing that vessel delay caused the lost employment.
Whether the full lost profit is recoverable will depend on the contract and governing law.
A yard claims 90 days of permissible delay because a critical component arrived late.
The buyer discovers that the component was ordered months later than originally scheduled.
The buyer should challenge whether the event qualifies for contractual relief and whether the yard complied with notice and mitigation requirements.
A supplier problem is not automatically a valid 90-day extension.
A foreign buyer has paid USD 25 million in instalments.
Delay reaches the contractual cancellation threshold.
The buyer decides that continued construction is commercially unacceptable.
Before serving cancellation, counsel should verify the calculation of delay and simultaneously review the refund guarantee.
The cancellation notice and guarantee demand strategy should be coordinated carefully.
The foreign buyer should collect the shipbuilding contract, amendments, construction schedule, all delay notices, buyer objections, progress reports, class documentation, instalment records and refund guarantees.
Prepare a day-by-day calculation separating permissible, disputed and non-permissible delay.
Check every contractual deadline for objecting to the yard’s notices.
Review whether liquidated damages have begun accruing and when the cancellation threshold will be reached.
At the same time, check the expiry and enforceability of refund guarantees and investigate the yard’s financial condition.
The buyer should preserve charter, financing and substitute-vessel evidence supporting potential damages.
The objective is to avoid reaching the cancellation threshold only to discover that rights were waived, notices were missed or financial security expired months earlier.
Potentially yes. Shipbuilding contracts commonly provide price reductions, liquidated damages or other remedies for non-permissible delivery delay.
No. Permissible delay, buyer-caused delay and other contractual extensions must be separated from non-permissible delay.
Potentially, where the event satisfies the contract and applicable law. Causation, notice and mitigation requirements can be crucial. (DergiPark)
Potentially, but recoverability depends on the contract, causation, proof and any exclusion or limitation of consequential losses.
Potentially yes. Many shipbuilding contracts establish an ultimate delay threshold permitting cancellation. The exact threshold must be taken from the individual contract.
Potentially in certain Turkish-law circumstances. TCO Article 473 can become relevant where delay attributable to the contractor makes timely completion clearly impossible. (Lexology)
The contract normally regulates repayment obligations. Any refund guarantee should be examined immediately to determine how repayment can be secured.
The yard may be entitled to an extension for buyer-caused delays where the contractual requirements are satisfied. The actual causal effect should still be examined.
A buyer should review and respond within the contractual deadline. Some contracts attach waiver consequences to failure to object promptly.
The shipbuilding contract, amendments, construction schedule, delay notices, buyer objections, progress reports, class records, variation orders, refund guarantee and evidence of financial losses are particularly important.
A newbuild vessel delivery dispute should be managed long before the contractual cancellation date arrives.
Foreign buyers should monitor every claimed extension and separate genuine permissible delays from construction delays attributable to the yard.
The contract should then be used to identify the buyer’s escalating remedies:
delay notice and reservation of rights, liquidated damages or price reduction, claims for additional recoverable losses, cancellation for excessive delay, refund of instalments and enforcement of refund security.
Particular attention should be paid to notice provisions. Public shipbuilding contracts demonstrate how short the periods for reporting and challenging delay claims can be.
The buyer should also monitor its financial security. If cancellation becomes likely, refund guarantees, construction instalments and shipyard solvency can become just as important as the technical construction schedule.
Fırat Fesih Kaya Law Office assists foreign shipowners, shipping companies, vessel investors and international buyers with newbuild vessel delivery delays in Turkey, Turkish shipyard disputes, shipbuilding contract claims, liquidated damages, cancellation of shipbuilding contracts, refund of construction instalments, refund guarantees, defective newbuild vessels, sea trial disputes, lost charter claims, maritime litigation and international shipbuilding arbitration.
Phone: +90 312 434 22 22
Mobile: +90 532 769 22 22
Email: info@firatfesihkaya.av.tr
Address: Mevlana Boulevard No: 221, Yıldırım Tower, Balgat, Çankaya, Ankara, Turkey