Yes. A foreign property owner whose building has been officially determined to be risky can challenge the determination where the applicable legal requirements are satisfied.
The most important issue is timing.
Under the current procedure, a building owner or legal representative may object to a risky building determination within 15 days from the final day of the relevant local announcement. The objection is submitted to the competent Urban Transformation Directorate or, where authority has been delegated, the relevant administration.
For foreign homeowners, this deadline creates a particular risk because the owner may be outside the country when the assessment, announcement and notification procedures take place.
A foreign owner should therefore never assume that the objection period begins only when a physical letter is personally received abroad.
Lawyer Fırat Fesih Kaya recommends treating any information that a property has been declared risky as urgent until the official notification chronology has been established.
Before challenging anything, determine what has actually happened.
A contractor may tell owners that the building is unsafe. A building manager may announce that urban transformation has started. An engineer may have inspected the building. Owners may already be negotiating reconstruction.
None of these circumstances should automatically be treated as proof that the statutory risky building determination has become final.
Under the official procedure, the risky building assessment report is submitted to the competent authority. The authority reviews the report and can return it to the licensed institution or organization if deficiencies or errors are identified. If the report is found appropriate and the building is determined to be risky, the relevant title authority is notified and the statutory notification procedure follows.
The foreign owner should therefore obtain the actual risky building documentation before deciding how to challenge the process.
The technical report is one of the most important documents in any challenge.
An objection should not be prepared solely on the basis of statements such as:
“I do not believe the building is dangerous.”
“The building has survived previous earthquakes.”
“There are no visible cracks.”
“The contractor only wants to redevelop the land.”
These concerns may explain why the owner is suspicious of the process, but the formal challenge should focus on the technical and procedural validity of the risky building determination.
The assessment is required to comply with the technical principles applicable to risky building determinations. The current implementing regulation also requires the official assessment process to use the designated electronic system.
The actual report should therefore be examined rather than challenged in the abstract.
A risky building determination cannot be created merely by an informal contractor opinion.
The statutory procedure requires the assessment to be carried out within the authorized framework. Owner-initiated assessments are conducted through licensed institutions or organizations, while the competent public authorities may also conduct or arrange assessments in circumstances provided by the legislation.
When reviewing a potential challenge, establish:
Who conducted the assessment?
Was the entity authorized to perform the statutory assessment?
Was the correct property assessed?
Does the report identify the correct building?
Was the assessment processed through the required official system?
Was the report reviewed by the competent authority?
These questions can be as important as the substantive engineering conclusions.
This is often the most important step for a foreign owner.
The current procedure provides that information concerning the risky building determination is posted on the building, owners are informed through the electronic government system, and the matter is announced at the relevant local administrative office for fifteen days. Risky buildings are also announced through the competent authority’s publication mechanism for fifteen days.
The risky building assessment is deemed notified to holders of relevant rights on the final day of the local announcement.
This deemed-notification rule directly affects the objection deadline.
The ordinary administrative objection period is 15 days from the final day of the relevant local announcement.
The objection must be submitted by the building owner or legal representative to the competent Urban Transformation Directorate or, where authority has been delegated, the relevant administration.
This means that two different fifteen-day periods should not be confused.
First, there is the period during which the relevant local announcement is displayed.
Then, from the final day of that announcement, the owner has the statutory fifteen-day objection period.
The precise dates should always be confirmed from the official records.
This is one of the most important issues for international property owners.
A foreign owner should not assume that failure to receive a physical letter at an overseas address prevents the statutory deadline from running.
The current framework uses building posting, electronic notification and local announcement mechanisms, and the risky building assessment is deemed notified on the final day of the relevant local announcement.
Therefore, a person who learns about the decision several weeks later may discover that the ordinary 15-day objection period has already expired.
If you own property but spend substantial periods outside the country, monitoring the property and official process is essential.
The current implementing regulation provides that the objection can be made by the building owner or legal representative.
It also addresses the position where the owner has died. The authority checks whether the objection was submitted within the statutory period and whether it was made by a person legally entitled to object. Untimely objections and objections made by persons who do not satisfy the relevant ownership or representative requirements are not processed under the ordinary mechanism.
A foreign owner using a representative should therefore ensure that the representative has sufficient authority to file the objection.
A foreign property owner can act through an appropriately authorized legal representative.
This is particularly important for owners who cannot return during the short objection period.
The power of attorney should be examined to ensure that it covers the necessary representation.
At the same time, a foreign owner should avoid granting unrelated and unnecessarily broad powers merely because urgent representation is required.
Authority to challenge a risky building determination does not inherently require unrestricted authority to sell the property, mortgage it or transfer ownership rights to a contractor.
A strong objection should identify the risky building determination being challenged and explain the technical or procedural concerns requiring review.
The exact arguments depend on the assessment.
Potential issues may involve the identity of the assessed structure, technical methodology, information used in the report, structural analysis, sampling or testing issues, inconsistencies in the report, or compliance with the applicable assessment principles.
The objection should not be treated merely as a declaration that the owner does not consent to urban transformation.
The central issue is whether the official conclusion that the building qualifies as risky is technically and legally sustainable.
In a technically disputed case, independent engineering review can be extremely valuable.
The risky building determination is fundamentally based on technical data.
A lawyer can examine notification, deadlines, administrative procedure and legal consequences, but questions concerning structural calculations, material data and engineering methodology may require specialist technical analysis.
For significant property disputes, coordinating legal and technical review can therefore provide a much stronger basis for deciding whether an objection is justified.
Personal opposition to demolition is not the same as demonstrating that the risky building determination is technically incorrect.
An owner may have understandable reasons for wanting to preserve the existing property.
The apartment may have substantial market value. It may have been renovated recently. It may produce rental income. The owner may distrust the proposed contractor.
Those issues can become relevant in other parts of the urban transformation process, but they do not necessarily invalidate the underlying technical determination.
The objection should therefore focus on the validity of the risky building assessment itself.
A statutory technical committee reviews objections to risky building determinations.
Current official guidance states that the technical committee examines the risky building assessment report technically as a whole and is not limited to the particular objection ground written in the owner’s petition. The committee determines whether the report was prepared in accordance with the applicable technical assessment principles and ultimately decides whether the building is risky or not.
This is an important protection.
It means the technical review is not necessarily confined to one isolated error identified by the property owner.
The technical committee can reach a final technical conclusion concerning whether the building qualifies as risky.
If the outcome of the risky building determination changes following the objection, the resulting change is communicated to the relevant title authority. The regulation also expressly recognizes that the result can change following a judicial decision.
Accordingly, an objection is not merely symbolic.
A successful technical challenge can alter the official status of the property.
If the objection is rejected, the risky building determination becomes final.
The same occurs where no objection is filed within the statutory period.
Once finalization occurs, the procedure moves toward evacuation and demolition.
At that point, the owner should immediately reassess legal strategy.
The question is no longer limited to challenging the technical report. The owner must also protect the title position, land share, existing apartment evidence and rights in the subsequent redevelopment.
If the result of the risky building determination changes following the objection, the competent authority communicates the changed status to the relevant title authority.
The practical consequences depend on the technical committee’s decision and the stage reached by the administrative process.
A successful objection can therefore prevent the owner from being forced to proceed on the basis of an incorrect risky building determination.
The administrative objection procedure should be distinguished from judicial review.
Depending on the circumstances, an owner may also need to consider challenging the relevant administrative action before the competent administrative court.
The appropriate defendant, time limit, challenged administrative action and requested judicial protection depend on the particular file and procedural stage.
Foreign owners should therefore avoid relying on a generic court petition or an old example obtained online.
The complete administrative file should be reviewed before litigation strategy is determined.
No automatic assumption should be made that filing a lawsuit alone stops the risky building process.
This distinction is extremely important.
If the owner seeks to prevent implementation of an administrative action while litigation is pending, the availability and requirements of interim judicial protection must be examined separately.
Waiting until demolition is imminent can significantly increase risk.
Once a structure has physically been demolished, later judicial success may not restore the former building in practical terms.
Missing the ordinary administrative objection period is serious.
The implementing regulation states that objections submitted outside the statutory period are not processed through the ordinary objection mechanism.
However, a missed administrative objection period should not automatically be interpreted as meaning that every possible legal question has disappeared.
The owner should investigate how notification occurred, what administrative actions have subsequently been taken, whether there are procedural irregularities, and whether judicial review remains available concerning an actionable administrative measure.
The available strategy depends heavily on the specific chronology.
Notification can be a critical part of the case.
Because the statutory system now relies on building posting, electronic notification and local announcement, the relevant question is not simply whether an overseas letter was received.
The actual administrative file should be examined to determine whether the statutory notification steps were carried out correctly and on which dates.
If a foreign owner believes the objection period was calculated incorrectly, the notification documents should be obtained before reaching a conclusion.
The identity of the building should be checked carefully.
The current regulation requires the risky building report to contain the address and building code recorded in the relevant national address database.
Where there is a dispute concerning parcel information, building identity or which physical structure was actually examined, these matters can be important in reviewing the validity of the assessment.
The title record, address information and technical report should therefore be compared.
The current regulation generally provides for only one risky building assessment report for each structure, subject to specified exceptions.
Exceptions include circumstances where a new report becomes necessary following an objection or judicial decision, where the report is determined to have been prepared contrary to reality, or where a concrete event affecting the building’s risk status occurs other than deliberate interference.
An owner should therefore not assume that an unfavorable official report can simply be replaced by repeatedly commissioning new statutory reports until a preferred result is obtained.
The correct challenge mechanism should be used.
No reliable legal strategy is created by physically obstructing the assessment.
The current regulation allows the competent authority to seek written authorization and law-enforcement assistance where access to the building or relevant independent units is prevented. Closed areas may be opened where necessary under the statutory procedure.
If an owner believes the assessment is unlawful, the proper response is to preserve evidence and use the available administrative and judicial remedies.
Usually, the fact that you did not consent to the initial assessment is not enough by itself.
The ordinary risky building assessment can be initiated by a qualifying owner or legal representative. It does not generally require unanimous consent from every apartment owner.
Therefore, a challenge should not be based solely on:
“I never authorized my neighbor to have the building assessed.”
Instead, determine whether the applicant had the necessary ownership status and whether the assessment itself complied with the applicable technical and administrative rules.
Appearance alone is generally insufficient.
The legal concept of a risky building is based on scientific and technical assessment rather than ordinary visual impressions.
A building may look well maintained while having significant structural weaknesses.
Conversely, visible deterioration does not mean that every statutory technical requirement was necessarily satisfied correctly.
The proper approach is to examine the technical report.
The procedural consequences depend on the type and stage of the challenge.
A timely statutory objection prevents the risky building determination from reaching finality through the no-objection route until the objection is evaluated.
If the technical committee rejects the objection, the determination becomes final and the evacuation and demolition stage follows.
Where court proceedings are involved, the owner should separately determine whether any interim judicial protection has been requested or granted rather than assuming litigation automatically suspends implementation.
Once the risky building determination becomes final, the competent authority proceeds with the evacuation and demolition procedure.
The current rules provide for notification through building posting, electronic notification and a fifteen-day local announcement. The evacuation and demolition action is deemed notified on the final day of that announcement.
Owners are then given a period not exceeding 90 days for evacuation and demolition.
This is why challenging the original risky building determination should be considered before the process reaches the final demolition stage.
Potentially.
Where the building has been determined to be risky but the owners wish to pursue strengthening rather than demolition, the current regulation provides a specific route.
Within the period given for demolition, technical feasibility must be established, the required owner decision must be obtained, a strengthening project must be prepared, and the necessary permit must be secured. Once strengthening has been properly completed within the period determined by the permitting authority, an application can be made for removal of the risky building notation from the title record.
Challenging the risk assessment and seeking strengthening are therefore legally different strategies.
A foreign owner should not focus exclusively on the objection and ignore the possibility that it may ultimately be rejected.
While the challenge is being evaluated, collect and preserve documents concerning the property.
Obtain the current title record.
Verify the registered land share.
Check mortgages, attachments and other restrictions.
Preserve photographs and videos of the apartment.
Record the floor, orientation, room configuration, balconies, parking, storage and other valuable characteristics.
Keep copies of architectural plans and existing ownership documents.
If the risky building determination ultimately becomes final, these materials may become important during redevelopment.
Technical objection and redevelopment negotiations are separate matters.
A contractor may pressure owners to sign while the risky building procedure is still being disputed.
Do not assume that signing is necessary merely to preserve your rights.
Before entering a redevelopment agreement, examine the exact replacement unit, construction contribution, completion date, temporary rental arrangements, delay provisions, contractor security and proposed title transfers.
The objection process should not be used to rush the owner into an unfavorable private contract.
The fact that other owners are negotiating with or supporting a contractor does not determine whether the risky building report is technically correct.
These are separate issues.
Once risky status becomes final, however, the subsequent redevelopment decision-making rules become increasingly important. Current official guidance provides for owner meetings and specified decisions under the applicable share-based simple-majority framework.
A foreign owner should therefore monitor both files simultaneously: the risky building challenge and the emerging redevelopment process.
You do not necessarily need every other owner to join your statutory objection.
The right to object belongs to qualifying owners or their legal representatives under the current procedure.
The technical committee’s task is to evaluate the technical validity of the risky building report, not to count how many owners prefer demolition.
A technically valid objection does not become invalid merely because the other owners want a new building.
Commercial motivation and structural risk are different questions.
Owners may strongly favor demolition because redevelopment could increase property values.
That does not replace the statutory technical assessment.
Likewise, an owner’s financial desire to keep the existing apartment does not prove that the building is safe.
The risky building challenge should therefore remain focused on the legality and technical validity of the assessment.
A foreign owner considering a challenge should obtain the risky building assessment report, documentation concerning the institution that prepared it, the administrative review information, title record, building and parcel information, notification documents, dates of local announcements, electronic notification information and any existing objection or technical committee documents.
If redevelopment has already started, also obtain owner-meeting records, contractor proposals and proposed redevelopment agreements.
The goal is to reconstruct the complete chronology rather than relying on verbal explanations.
The first step is deadline control. Determine the final day of the local announcement and calculate whether the statutory 15-day objection period remains open.
The second step is document control. Obtain the actual risky building report, title information and notification records.
The third step is technical review. If there is a genuine dispute over the assessment, consider independent engineering analysis so that the objection addresses substantive technical issues rather than general dissatisfaction.
The fourth step is administrative objection. Submit the objection to the competent authority within the statutory period and ensure that the applicant has the correct ownership or representative status.
The fifth step is judicial strategy. If the administrative objection is rejected, or if another actionable administrative irregularity exists, determine promptly whether judicial review and interim protection should be pursued.
The sixth step is property protection. Do not wait for the challenge to end before verifying the title, land share, restrictions and physical characteristics of the existing apartment.
The seventh step is redevelopment monitoring. Other owners may begin organizing the future project once risky status becomes final. Do not ignore owner meetings, contractor documents or subsequent statutory notices merely because you disagree with the original risky building determination.
For a foreign property owner, the key principle is:
Challenge the risky building determination through the legal and technical procedure, not by simply refusing demolition or refusing to communicate with the other owners. The 15-day objection period can make early action decisive.
Yes. A foreign owner with the relevant ownership status can use the statutory objection mechanism. The ordinary procedure allows building owners or their legal representatives to object.
The current procedure provides 15 days from the final day of the relevant local announcement.
Do not assume the deadline has not started. The current notification procedure includes building posting, electronic notification and local announcement, and the assessment is deemed notified on the final day of the relevant local announcement.
The objection is submitted to the competent Urban Transformation Directorate or, where authority has been delegated, the relevant administration for the location of the building.
The objection is reviewed by the statutory technical committee, which examines the risky building report technically as a whole rather than being limited only to the specific objection ground stated in the petition.
Not simply because you dislike the result. The current regulation generally allows one risky building assessment report per structure, subject to specified exceptions such as a new report required after an objection or judicial decision.
You should not assume so. Judicial review and interim protection are separate procedural questions and should be evaluated according to the particular case.
The risky building determination becomes final, and the process can proceed toward evacuation and demolition.
Under the current framework, the administration gives owners a period not exceeding 90 days for evacuation and demolition.
Obtain the official report and notification records, establish the final day of the local announcement, calculate the 15-day objection deadline, arrange technical review where necessary and obtain legal review before the statutory period expires.
A risky building challenge can become time-sensitive very quickly. The most serious mistake for a foreign owner is often waiting for a personal overseas notification while the statutory announcement and objection periods are already progressing.
The critical issues include the 15-day objection deadline, technical validity of the risky building report, notification procedure, technical committee review, possible judicial proceedings, interim protection and preservation of property rights before demolition.
Fırat Fesih Kaya Law Office provides legal assistance to foreign homeowners and property investors facing risky building and urban transformation disputes.
Lawyer Fırat Fesih Kaya assists foreign clients with reviewing risky building reports, calculating objection deadlines, preparing challenges to risky building determinations, coordinating technical review, examining notification irregularities, assessing judicial remedies, reviewing title and land-share records and protecting property rights throughout the subsequent urban transformation process.
Phone: +90 312 434 22 22
WhatsApp: +90 532 769 22 22
Email: info@firatfesihkaya.av.tr