Received products from a Turkish supplier that fail agreed technical specifications? Learn about CISG nonconformity, rejection rights, inspection deadlines, replacement goods, contract avoidance, refunds, damages and legal remedies.
A foreign buyer who receives goods from a Turkish supplier that fail to meet agreed technical specifications may face serious commercial and financial consequences. Products that do not satisfy contractual requirements may be unsuitable for their intended purpose, incompatible with existing equipment, unsafe for use, or impossible to resell in the destination market.
International companies frequently purchase machinery, automotive components, electrical equipment, industrial materials, chemicals, textiles, construction products, medical equipment, packaging, and customized manufactured goods from Turkish suppliers.
These transactions often involve detailed technical specifications, engineering drawings, approved samples, manufacturing standards, performance requirements, testing protocols, and product certification obligations.
Before production begins, the foreign buyer may provide precise technical requirements.
The supplier may confirm that the goods will comply with those specifications.
However, disputes arise when the delivered products differ from the agreed requirements.
For example, a foreign manufacturer may purchase industrial components with specified dimensions and tolerances but receive products that cannot be installed in its production equipment.
In another case, an international distributor may order electrical devices with particular voltage, power, or safety specifications but receive products that fail technical testing.
More serious situations may involve incorrect chemical composition, reduced load capacity, incompatible materials, missing safety features, inaccurate calibration, insufficient durability, or products manufactured under the wrong technical standard.
The foreign buyer may discover the problem during customs inspection, warehouse examination, installation, commissioning, laboratory testing, or customer use.
The Turkish supplier may argue that the differences are minor, that the products remain commercially usable, or that the buyer approved an alternative specification.
The buyer may face additional testing expenses, replacement purchases, delayed projects, customer penalties, product recalls, and lost profits.
These circumstances raise important legal questions.
Can a foreign buyer reject goods that do not meet agreed technical specifications? Can the buyer demand replacement or repair? Can the contract be cancelled? Can the buyer recover an advance payment? Can the buyer claim compensation for installation costs, project delays, lost profits, and customer claims? What evidence is required to prove technical nonconformity?
Under Turkish law and applicable international sales rules, delivery of goods that fail to satisfy agreed technical specifications may constitute contractual nonconformity and give rise to buyer remedies.
However, the available remedies depend on the governing law, contractual specifications, seriousness of the deviation, inspection and notification requirements, and resulting damage.
For qualifying international sales, the United Nations Convention on Contracts for the International Sale of Goods (CISG) may apply.
Article 35 establishes important conformity requirements.
Articles 38 and 39 establish inspection and notification obligations.
Articles 45–52 regulate buyer remedies.
Articles 74–77 establish important rules concerning damages and mitigation.
Where Turkish domestic sales law applies, Articles 219–231 of the Turkish Code of Obligations No. 6098 establish important rules concerning defective goods.
Article 23 of the Turkish Commercial Code No. 6102 may establish additional notification requirements for certain commercial sales between merchants.
This guide explains how foreign buyers can prove technical nonconformity, reject defective goods, recover payments, claim damages, and pursue legal remedies against Turkish suppliers under the 2026 legal framework.
Incorrect technical specifications arise where delivered goods fail to satisfy agreed technical characteristics.
For example, a contract may require machinery components with specified dimensions, materials, performance levels, or safety standards.
The supplier may deliver products that differ from those requirements.
However, the legal consequences depend on the contractual specifications and applicable law.
The buyer must establish the relevant deviation.
Potentially.
A supplier may breach the agreement where delivered goods fail to conform to binding technical requirements.
For example, a manufacturer may deliver components with incorrect dimensions.
However, the buyer must establish that the specifications formed part of the contract.
The supplier may dispute the relevant technical requirements.
The court or arbitral tribunal must examine the evidence.
Article 35 requires goods to conform to the quantity, quality, description, and packaging required by the contract.
The provision also establishes supplementary conformity standards unless the parties have agreed otherwise.
For example, goods may need to be suitable for their ordinary purpose or a particular purpose made known to the seller under the relevant conditions.
Incorrect technical specifications may therefore constitute nonconformity.
However, the statutory requirements must be satisfied.
Potentially, but unauthorized deviations may constitute nonconformity.
For example, a buyer may order components with specified dimensions.
The supplier may deliver parts that are too large or too small.
The difference may prevent installation or assembly.
However, the contract may permit manufacturing tolerances.
The relevant specifications must be examined.
Potentially, but the deviation may breach the agreement.
For example, the contract may specify dimensional tolerances of a particular range.
The delivered products may exceed those limits.
The buyer may possess remedies under the applicable law.
However, the deviation must be established through reliable measurement.
Potentially.
However, a machine that fails agreed performance requirements may be nonconforming.
For example, the contract may require a specified production capacity.
The delivered machine may operate below that capacity.
The buyer should preserve performance test results.
The legal consequences depend on the agreement and circumstances.
Potentially.
However, incorrect voltage specifications may create serious conformity and safety concerns.
For example, a buyer may order equipment designed for a particular electrical system.
The supplier may deliver incompatible products.
The buyer may possess contractual remedies.
Technical testing and documentation may be important.
Potentially.
The contract may require specified power output or consumption characteristics.
The supplier may deliver products that do not satisfy those requirements.
The legal consequences depend on the agreement.
The buyer should establish the actual performance through appropriate testing.
Potentially.
However, unauthorized material differences may constitute nonconformity.
For example, a buyer may require a particular steel grade or chemical composition.
The supplier may use a different material.
The buyer may need laboratory testing.
The relevant contractual specifications must be established.
Potentially.
However, products that fail agreed load capacity requirements may be unsuitable or unsafe.
For example, industrial equipment may be designed to support a specified weight.
The delivered product may fail testing.
The buyer should preserve technical evidence.
The legal consequences depend on the contract and applicable law.
Potentially.
For example, the contract may require components capable of operating within a specified temperature range.
The supplier may deliver products that fail those requirements.
The buyer may possess remedies concerning nonconformity.
However, the actual performance must be established.
Potentially.
For example, industrial components may need to resist specified chemicals.
The supplier may deliver materials that deteriorate under the agreed operating conditions.
The buyer should preserve test results and technical specifications.
The legal consequences depend on the agreement.
Potentially.
The contract may require specified durability or service life characteristics.
However, durability claims must be assessed according to the agreed testing standards.
For example, a product may fail prematurely during normal use.
The buyer must establish the relevant nonconformity and causal connection.
Potentially.
For example, measuring equipment may require calibration within specified tolerances.
The supplier may deliver devices that produce inaccurate readings.
The buyer may possess remedies under the applicable law.
Calibration records and independent testing may be important.
Potentially.
Machinery or electronic products may contain software required for operation.
For example, the contract may specify particular functionality or compatibility.
The delivered equipment may lack those features.
However, the applicable legal classification may involve goods, software licensing, or mixed contractual obligations.
The relevant framework must be examined.
Potentially.
However, missing safety features may create serious contractual and regulatory concerns.
For example, machinery may lack agreed protective systems.
The buyer may be unable to use or resell the equipment lawfully.
The legal consequences depend on the contract and applicable safety requirements.
Potentially.
However, the supplier’s responsibility depends on the contract and applicable law.
For example, the buyer may require compliance with a specified technical standard.
The supplier may deliver goods that fail the standard.
The buyer must establish the relevant obligation and nonconformity.
Potentially, but missing documentation may constitute a separate contractual breach.
For example, the agreement may require test certificates or declarations of conformity.
The supplier may fail to provide them.
However, the absence of a certificate does not automatically prove that the goods are physically defective.
The documentary and technical obligations must be examined separately.
Potentially.
The supplier may argue that deviations fall within acceptable manufacturing tolerances.
However, the buyer may establish that the differences affect functionality or safety.
The legal consequences depend on the contract and commercial significance.
The court or arbitral tribunal must examine the evidence.
Potentially.
However, commercial usability does not automatically establish contractual conformity.
For example, a machine may operate but fail the agreed production capacity.
The buyer may have contracted for specific performance characteristics.
The relevant contractual requirements must be examined.
Potentially.
The contract may permit equivalent products or materials.
However, the supplier must establish that the delivered goods satisfy the agreed equivalence requirements.
The buyer may dispute technical equivalence.
Expert examination may be necessary.
Not automatically.
Where specifications are contractually binding, unilateral changes may constitute breach.
However, the contract may permit specified modifications.
For example, the supplier may be authorized to use equivalent components.
The relevant terms must be examined.
Potentially.
The supplier may rely on emails, revised drawings, or other communications.
However, the approval must be established.
For example, the buyer may approve a limited technical modification.
The supplier cannot automatically treat that approval as authorization for unrelated changes.
Potentially.
The parties may agree on revised specifications.
However, the supplier must establish which version was contractually binding.
For example, multiple drawing revisions may exist.
The buyer should preserve approval records and version histories.
The court must interpret the agreement.
Potentially.
The supplier may argue that the buyer’s technical instructions caused the problem.
However, the legal consequences depend on the contract and applicable law.
For example, the supplier may have been required to follow the buyer’s drawings.
The buyer’s role in preparing specifications may be relevant.
The statutory requirements must be examined.
Potentially.
An approved sample may provide evidence concerning agreed product characteristics.
However, the buyer may argue that the sample did not reflect the final technical specifications.
The court must examine the agreement.
The legal consequences depend on the relationship between samples and written requirements.
Potentially.
The supplier may argue that the specifications were indicative rather than binding.
However, the buyer may possess evidence showing that they were mandatory.
For example, the purchase order may expressly require compliance with a particular technical standard.
The court must interpret the contractual documents.
Potentially.
The available remedy depends on the governing law and seriousness of the nonconformity.
Under the CISG, avoidance generally requires a fundamental breach under Article 49.
Other remedies may include replacement, repair, price reduction, or damages.
The buyer should not assume that every minor deviation automatically permits rejection of the entire shipment.
Article 25 defines fundamental breach.
The concept concerns a breach that substantially deprives the other party of what it was entitled to expect under the contract, subject to the foreseeability qualification.
For example, machinery that cannot perform its agreed function may constitute a fundamental breach in appropriate circumstances.
However, the legal assessment depends on the facts.
Potentially.
Article 49 of the CISG permits avoidance where the seller’s breach is fundamental and the relevant requirements are satisfied.
For example, goods may be completely unsuitable for their intended purpose.
However, cancellation is not automatically available for every deviation.
The buyer must comply with applicable procedural requirements.
Potentially.
However, the legal consequences depend on the extent of the nonconformity.
For example, some products may satisfy the agreed specifications while others do not.
Article 51 of the CISG may become relevant.
Avoidance of the entire contract may require additional conditions.
Potentially.
Where only part of the shipment is nonconforming, the buyer may possess remedies concerning that portion.
However, the contract and applicable law must be examined.
The buyer should identify the defective products.
The appropriate remedy depends on the circumstances.
Potentially.
Customs clearance does not automatically establish contractual acceptance of technical conformity.
However, the buyer must comply with applicable inspection and notification obligations.
For example, technical defects may become apparent only during installation.
The relevant deadlines must be examined.
Potentially.
However, installation may affect the available remedies and evidence.
For example, a machine may fail performance testing after installation.
The buyer should preserve commissioning records and technical reports.
The applicable law must be examined.
Potentially.
Use of goods may affect restitution and particular remedies.
However, use does not automatically eliminate every claim.
For example, hidden technical defects may become apparent only during operation.
The buyer should examine the applicable legal framework.
Potentially.
Article 46(2) of the CISG permits replacement where the lack of conformity constitutes a fundamental breach and the relevant requirements are satisfied.
For example, the buyer may demand components meeting the agreed specifications.
However, replacement is not automatically available for every minor deviation.
The request must comply with applicable timing requirements.
Potentially.
Article 46(3) of the CISG permits repair unless unreasonable in the circumstances.
For example, a machinery defect may be corrected through replacement of a component.
However, repair may be impractical where the entire product is manufactured incorrectly.
The circumstances must be examined.
Potentially.
Where the technical problem can be corrected through calibration, the buyer may seek appropriate performance.
However, the available remedy depends on the contract and governing law.
For example, measuring equipment may require adjustment.
The supplier’s cure rights and obligations must be examined.
Potentially.
Where the delivered equipment lacks agreed software functionality, corrective updates may be appropriate.
However, the legal consequences depend on the contract and applicable law.
The buyer should identify the missing functionality.
The supplier may possess a right to cure under specified circumstances.
Potentially.
Article 50 of the CISG establishes an important price reduction remedy.
The reduction generally reflects the relationship between the value of the goods actually delivered and the value conforming goods would have had at delivery.
However, the statutory conditions and seller’s cure rights must be examined.
The buyer should preserve valuation evidence.
Potentially.
Where the contract is validly avoided, Articles 81–84 of the CISG establish important restitution rules.
For example, the buyer may have prepaid for machinery that fails essential technical requirements.
If the buyer validly avoids the agreement, repayment may be available.
However, the statutory requirements must be satisfied.
Potentially.
The appropriate remedy depends on the contract and governing law.
For example, valid avoidance may create restitution rights.
However, the buyer may also possess alternative remedies.
The buyer must establish the relevant legal basis.
Potentially.
The buyer may possess contractual defenses or suspension rights under the applicable framework.
For example, the supplier may demand final payment despite failed acceptance testing.
However, withholding payment without a legally sufficient basis may create additional liability.
The buyer should examine the contract.
Yes, where the applicable legal requirements are satisfied.
Article 45 of the CISG establishes important buyer remedies for seller nonperformance.
Articles 74–77 regulate damages.
For example, technical nonconformity may cause replacement purchases, installation expenses, or project delays.
However, the buyer must establish the relevant loss and causal connection.
Article 74 establishes the general damages framework for breach of contract.
Damages may include loss suffered and loss of profit, subject to the foreseeability limitation.
For example, defective machinery may prevent the buyer from completing customer orders.
However, the claimant must establish the relevant financial loss.
The court or arbitral tribunal must examine the evidence.
Potentially.
The buyer may incur expenses installing goods that later prove nonconforming.
However, recovery depends on the applicable legal framework.
The buyer must establish that the costs were caused by the supplier’s breach.
The reasonableness of the expenses may be important.
Potentially.
Commissioning expenses may arise when machinery is tested or prepared for operation.
For example, the buyer may hire engineers to conduct acceptance testing.
However, reimbursement depends on the governing law and causal connection.
The relevant invoices and reports should be preserved.
Potentially.
The buyer may arrange independent testing to establish nonconformity.
For example, laboratory analysis may identify incorrect material composition.
However, the buyer must establish that the expense was reasonable and caused by the breach.
The relevant reports should be preserved.
Potentially.
The buyer may incur expenses correcting technical defects.
However, the applicable law and supplier’s cure rights must be examined.
For example, the buyer may hire a third party to repair machinery.
The recoverability of those costs depends on the circumstances.
Potentially.
Article 75 of the CISG establishes important rules concerning substitute transactions following valid avoidance.
For example, the buyer may purchase conforming equipment from another supplier at a higher price.
However, the statutory conditions must be satisfied.
The replacement purchase should be commercially reasonable.
Potentially.
Incorrect technical specifications may delay installation or production projects.
However, the buyer must establish the relevant loss and causal connection.
For example, a delayed project may generate additional contractor expenses.
The court must examine foreseeability and the applicable damages framework.
Potentially.
Article 74 permits recovery of qualifying lost profits.
For example, defective machinery may prevent the buyer from fulfilling confirmed customer orders.
However, speculative future revenue does not automatically establish recoverable loss.
The buyer must establish the relevant financial consequences.
Potentially.
The buyer may face penalties from downstream customers because of defective products.
However, recovery from the Turkish supplier depends on the governing law and circumstances.
The buyer must establish the relevant contractual obligations and financial loss.
Not every penalty paid to a third party is automatically recoverable.
Potentially.
Incorrect technical specifications may create safety or regulatory concerns.
The buyer may need to withdraw products from the market.
However, the applicable legal requirements depend on the product and destination country.
The buyer must establish the relevant costs and causal connection.
Potentially.
Nonconforming goods may create customs-related expenses.
For example, the buyer may need to return or re-export the products.
However, the allocation of responsibility depends on the contract, Incoterms, and applicable law.
The buyer must establish the relevant loss.
Potentially.
Defective goods may remain in storage while the dispute is resolved.
However, the buyer must establish that the expenses were reasonable and caused by the breach.
The relevant invoices should be preserved.
Potentially.
Nonconforming goods may remain at a port or terminal beyond the applicable period.
However, the legal consequences depend on the shipping arrangements and cause of delay.
The buyer must establish the relevant loss and causal connection.
Potentially, but the legal requirements may be difficult to establish.
For example, defective products may damage the buyer’s commercial reputation.
However, the claimant must identify legally recoverable damage.
General allegations of reputational harm do not automatically establish compensation.
Yes.
Article 77 of the CISG establishes a duty to take reasonable measures to mitigate loss.
For example, the buyer may need to arrange appropriate repairs or replacement purchases.
However, the buyer is not automatically required to accept unreasonable costs or risks.
Failure to mitigate may reduce recoverable damages.
Potentially.
Article 48 of the CISG establishes important seller cure rights under specified circumstances.
For example, the supplier may offer to replace defective components.
However, the buyer’s rights and the reasonableness of the proposed cure must be examined.
A cure offer does not automatically eliminate every damages claim.
Potentially.
The legal consequences depend on the contract and applicable law.
For example, repair may cause unreasonable delay or fail to address the technical problem.
However, the buyer cannot automatically reject every cure proposal without considering the applicable framework.
The court or arbitral tribunal must examine the circumstances.
Potentially.
However, the buyer’s rights depend on the contract and seriousness of the breach.
For example, replacement goods may arrive after a critical project deadline.
The buyer may possess remedies concerning delay and nonconformity.
The applicable statutory requirements must be examined.
Potentially.
Article 38 of the CISG establishes inspection obligations.
However, the required inspection depends on the circumstances.
For example, complex machinery may require commissioning before technical defects can be identified.
The court must examine what inspection was practicable.
Article 38 requires the buyer to examine the goods, or cause them to be examined, within as short a period as practicable in the circumstances.
However, the timing depends on the delivery arrangement and nature of the goods.
For example, technical testing may require specialized equipment.
The buyer should not assume that inspection can be delayed indefinitely.
Article 39 requires the buyer to notify the seller of the lack of conformity within a reasonable time after discovering it or when it ought to have discovered it.
The notice must specify the nature of the nonconformity.
Article 39(2) generally establishes an outer period of two years from actual handover, unless inconsistent with a contractual guarantee period.
However, Articles 40 and 44 may affect the consequences of certain notice failures.
The deadline depends on the governing law and contract.
Under the CISG, notice must generally be given within a reasonable time after discovery or when discovery should have occurred.
Under Turkish domestic commercial law, Article 23 of the Turkish Commercial Code establishes specific notification rules for certain commercial sales between merchants.
The buyer should identify the applicable framework promptly.
Article 23 establishes important rules concerning commercial sales between merchants.
For certain commercial sales, the buyer must notify the seller of obvious defects within two days.
Where the defect is not immediately apparent, the buyer must examine or have the goods examined within eight days and notify the seller within that period if a defect is discovered.
Other defects are subject to the applicable provisions of the Turkish Code of Obligations.
However, the precise application depends on the transaction and governing law.
No.
Where the CISG applies, its inspection and notification provisions generally govern the relevant issues.
Article 23 of the Turkish Commercial Code does not automatically replace the CISG in every international sale.
The contract and applicable legal framework must be examined.
Potentially.
Failure to comply with applicable notification requirements may affect the buyer’s remedies.
However, the legal consequences depend on the governing law.
Under the CISG, Articles 40 and 44 may become relevant in specified circumstances.
The buyer should preserve evidence concerning discovery and notification.
Article 40 limits the seller’s ability to rely on Articles 38 and 39 where the lack of conformity relates to facts the seller knew or could not have been unaware of and failed to disclose to the buyer.
For example, deliberate delivery of goods with known technical defects may raise questions under Article 40.
However, the statutory conditions must be established.
The buyer must prove the relevant facts.
Potentially.
Where the supplier knowingly concealed technical nonconformity, Article 40 may become relevant.
However, the buyer must establish the relevant knowledge and nondisclosure.
The existence of a technical defect does not automatically prove deliberate concealment.
The court or arbitral tribunal must examine the evidence.
Potentially.
The supplier may rely on inspection records or acceptance certificates.
However, factory inspection does not automatically eliminate every later conformity claim.
For example, certain defects may be hidden.
The legal consequences depend on the inspection scope and contract.
Potentially.
An acceptance certificate may provide evidence concerning product approval.
However, its legal effect depends on the wording and circumstances.
For example, the certificate may confirm only preliminary testing.
The buyer may still possess claims concerning hidden defects.
The applicable law must be examined.
Potentially.
Payment may be relevant to the parties’ conduct.
However, payment does not automatically establish that the goods satisfy every technical requirement.
For example, the buyer may pay before installation.
The applicable inspection and notification rules must be examined.
Potentially.
The supplier may argue that the buyer installed the goods incorrectly.
However, the buyer may claim that the products were already nonconforming.
The relevant technical evidence must be examined.
The court may require expert analysis.
Potentially.
The supplier may argue that the products were used outside their intended operating conditions.
However, the buyer may establish that the goods failed under agreed conditions.
The contract and technical specifications are important.
The court must examine the causal relationship.
Potentially.
However, the legal consequences depend on when the nonconformity arose.
For example, physical damage may occur during transport.
By contrast, incorrect dimensions or material composition may originate during manufacturing.
The buyer should distinguish manufacturing defects from transport damage.
Yes.
Incoterms may allocate delivery obligations, costs, and risk of loss.
However, they do not automatically replace contractual quality requirements.
For example, risk may transfer to the buyer at a specified point.
Nevertheless, the seller may remain responsible for nonconformity existing when risk passed under Article 36 of the CISG.
Not automatically.
Article 36 generally makes the seller responsible for nonconformity existing when risk passes, even if discovered later.
However, the statutory requirements must be satisfied.
The buyer must establish the relevant nonconformity.
Risk transfer does not automatically eliminate claims concerning manufacturing defects.
Yes.
Independent testing may help establish whether the goods satisfy agreed specifications.
For example, a buyer may commission dimensional measurement, performance testing, chemical analysis, or safety testing.
However, the evidentiary value depends on the methodology and circumstances.
The buyer should preserve representative samples and original records.
Yes.
The supplier may dispute the testing method, equipment, sample selection, or findings.
For example, the supplier may argue that the test conditions differed from the agreed standard.
The court or arbitral tribunal may require expert examination.
The buyer should preserve the complete testing documentation.
Yes, where expert examination is appropriate.
For example, a court may appoint an engineer to compare the delivered goods with contractual specifications.
However, the expert’s role is to provide specialized technical analysis.
The court determines the legal consequences.
The relevant procedural requirements must be satisfied.
Potentially.
Articles 400–405 of the Turkish Code of Civil Procedure No. 6100 establish mechanisms concerning preservation of evidence.
For example, the buyer may seek examination of goods stored in Turkey where there is a legally sufficient risk of evidence loss.
However, the statutory requirements must be satisfied.
Evidence preservation is not an unrestricted discovery procedure.
Potentially.
Articles 219 and following of the Turkish Code of Civil Procedure establish important rules concerning documentary evidence.
A court may order production of relevant documents under the applicable conditions.
For example, manufacturing test records may help establish whether the supplier complied with specifications.
The applicant must identify the documents and legal relevance.
Potentially.
Technical drawings may identify agreed dimensions, materials, tolerances, and performance requirements.
However, the buyer must establish that the drawings formed part of the contract.
The delivered goods may require expert comparison.
The relevant revisions and approval dates should be preserved.
Potentially.
Laboratory reports may establish material composition or performance characteristics.
However, the report must be relevant to the delivered goods.
The supplier may challenge the methodology.
The buyer should preserve the chain of custody.
Yes, potentially.
Factory acceptance tests may establish whether equipment satisfied specified requirements before shipment.
However, the legal effect depends on the contract and testing scope.
For example, a successful factory test may not address every operational condition.
The buyer should preserve the complete report.
Yes, potentially.
Site acceptance tests may establish whether equipment performs correctly after installation.
However, the results may be affected by installation conditions or other factors.
The buyer should preserve test procedures and technical data.
The court may require expert examination.
Potentially.
Photographs may show visible dimensional or design differences.
However, photographs may not establish complex performance or material characteristics.
The buyer should preserve original images where possible.
Technical testing may be necessary.
Potentially.
Videos may document equipment malfunction or failed testing.
However, authenticity and context must be examined.
The supplier may dispute the operating conditions.
The buyer should preserve original recordings and relevant test data.
Yes, potentially.
Emails may establish agreed requirements or supplier assurances.
For example, correspondence may confirm a particular performance standard.
The buyer should preserve the complete communication history.
The court or arbitral tribunal must examine the context.
Potentially.
Messages may contain discussions concerning specifications or unauthorized modifications.
However, authenticity and context must be examined.
A screenshot alone may not conclusively establish every relevant fact.
The buyer should preserve communications lawfully.
Yes, potentially.
A purchase order may identify the agreed specifications.
For example, it may refer to technical drawings or standards.
However, the legal effect depends on whether the terms became part of the contract.
The buyer should preserve the accepted order.
Potentially.
A proforma invoice may contain product descriptions and technical requirements.
However, the document does not automatically establish every contractual term.
The buyer should examine the complete agreement.
The relevant communications may also be important.
Potentially, where the conduct satisfies the elements of a recognized criminal offense.
For example, deliberate deception concerning product specifications may raise fraud questions.
Articles 157 and 158 of the Turkish Penal Code No. 5237 establish relevant provisions.
However, ordinary contractual nonconformity does not automatically constitute criminal fraud.
The prosecution must establish the statutory elements.
Potentially.
A supplier may allegedly provide fabricated technical reports or certificates.
The legal consequences depend on the nature of the document and conduct.
Articles 204 and 207 of the Turkish Penal Code regulate official and private document forgery.
However, an inaccurate certificate does not automatically establish criminal forgery.
Not automatically.
A criminal complaint concerns suspected criminal conduct.
Recovery of the purchase price may require separate commercial proceedings.
A criminal investigation does not automatically reverse payments.
The buyer should examine the appropriate contractual remedies.
Potentially.
The CISG may apply where the parties have their places of business in different Contracting States and the relevant conditions are satisfied.
It may also apply through applicable private international law rules in specified circumstances.
However, the parties may exclude the CISG under Article 6.
The buyer should examine the contract and governing law.
Yes.
Article 6 permits parties to exclude the CISG or derogate from specified provisions under the Convention’s framework.
However, the exclusion must be established through the contract and applicable interpretation rules.
A general choice of Turkish law does not necessarily exclude the CISG.
No.
The CISG forms part of the applicable legal framework in qualifying international sales.
A contractual choice of Turkish law does not automatically mean that domestic sales law replaces the CISG.
The parties may expressly exclude the Convention.
The relevant contractual wording must be examined.
Yes, where the CISG does not apply or has been validly excluded.
Articles 219–231 of the Turkish Code of Obligations establish important rules concerning defective goods.
Article 227 establishes specified buyer remedies.
Article 23 of the Turkish Commercial Code may establish additional requirements for commercial sales between merchants.
The buyer should identify the applicable framework.
Article 219 establishes important rules concerning the seller’s liability for defects.
The provision addresses defects that reduce or eliminate the value or expected usefulness of goods and the absence of promised qualities.
For example, products that fail agreed technical specifications may raise defect liability questions.
However, the statutory requirements must be satisfied.
Article 227 establishes important buyer remedies concerning defective goods under Turkish domestic sales law.
Depending on the statutory conditions, the buyer may seek rescission, price reduction, repair, or replacement.
The buyer may also possess compensation rights under the applicable framework.
However, the availability of each remedy depends on the circumstances.
Potentially.
Article 227 permits rescission under the applicable conditions.
However, the court may consider whether rescission is appropriate.
For example, a minor technical deviation may not justify termination of the entire transaction.
The buyer must establish the relevant legal requirements.
Potentially.
Article 227 recognizes replacement as a remedy where the statutory conditions are satisfied.
However, the nature of the goods and availability of conforming replacements may be important.
For example, replacement may be appropriate where the supplier can provide products meeting the agreed specifications.
The court must examine the circumstances.
Potentially.
Article 227 recognizes repair under the applicable conditions.
However, repair must be possible and appropriate.
For example, a machinery defect may be corrected through replacement of a component.
The relevant circumstances must be examined.
Potentially.
Article 227 recognizes price reduction as a remedy.
However, the amount must be determined under the applicable framework.
The buyer should preserve evidence concerning the value of conforming and nonconforming goods.
Expert examination may be necessary.
Article 231 establishes important limitation rules concerning defective goods under domestic sales law.
The general framework provides a two-year period from delivery for certain movable goods claims, subject to statutory exceptions and applicable contractual arrangements.
However, deliberate concealment of defects may affect the legal analysis.
The buyer should examine the specific transaction and governing law.
Potentially.
The competent court depends on the contract, jurisdiction agreement, and applicable procedural framework.
For example, a foreign buyer may bring a commercial claim before a competent Turkish commercial court where jurisdiction exists.
However, a valid arbitration agreement may require a different procedure.
The buyer should examine the dispute resolution clause.
Potentially.
The legal consequences depend on the contract and applicable jurisdiction rules.
For example, the parties may have agreed on foreign court jurisdiction.
However, the enforceability of the clause must be examined.
The buyer should also consider whether a foreign judgment can be enforced against the supplier’s assets.
Potentially.
Arbitration may be available where the parties have a valid arbitration agreement.
For example, the supply contract may provide for arbitration concerning technical nonconformity.
However, the buyer cannot automatically require arbitration without a legally sufficient basis.
The arbitration clause and procedural requirements must be examined.
Potentially.
Turkey is a party to the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards.
Foreign arbitral awards may be recognized and enforced under the applicable framework.
However, the statutory requirements and possible refusal grounds must be examined.
The buyer may need to pursue the relevant enforcement procedure.
Potentially.
Law No. 5718 establishes important rules concerning recognition and enforcement of foreign judgments.
However, the statutory requirements must be satisfied.
For example, a foreign buyer may obtain a judgment requiring repayment or damages.
The buyer may then seek enforcement against the supplier’s assets in Turkey.
The applicable procedure must be examined.
Potentially.
Precautionary attachment may be available under the Enforcement and Bankruptcy Law No. 2004 where the statutory requirements are satisfied.
For example, the buyer may possess a qualifying monetary claim concerning defective goods.
However, precautionary attachment is not automatically available in every technical specification dispute.
The court must examine the relevant conditions.
Security may also be required.
Potentially.
Articles 389 and following of the Turkish Code of Civil Procedure establish important rules concerning interim judicial protection.
For example, the buyer may seek preservation of disputed goods or technical evidence.
However, the court must examine the asserted right, urgency, and proportionality.
The requested measure must address a specific legal risk.
Potentially.
Where the buyer possesses an enforceable monetary claim, Turkish enforcement procedures may be available.
However, the supplier may possess procedural defenses.
The appropriate mechanism depends on the relevant judgment, arbitral award, or other enforceable instrument.
The applicable deadlines and requirements must be examined.
Yes.
A foreign buyer may appoint a Turkish lawyer to assist with commercial litigation and related proceedings.
The applicable authorization and procedural requirements must be satisfied.
Where documents are executed abroad, authentication and translation requirements may arise.
The buyer’s physical absence from Turkey does not automatically prevent legal action.
Relevant evidence may include the supply agreement, purchase order, technical specifications, engineering drawings, approved samples, manufacturing standards, quality certificates, laboratory reports, factory acceptance tests, site acceptance tests, payment records, shipping documents, customs records, photographs, videos, emails, and WhatsApp messages.
The buyer should identify the exact technical requirements.
The delivered goods should be compared with the agreed specifications.
The relevant inspection and notification dates should be documented.
Where complex technical defects are alleged, independent expert testing may be important.
The buyer should also preserve records concerning financial losses.
As of November 2026, several legal frameworks may govern disputes involving goods supplied from Turkey that fail agreed technical specifications.
The United Nations Convention on Contracts for the International Sale of Goods may apply to qualifying international sales.
Article 6 permits exclusion or modification of the Convention under the applicable conditions.
Article 25 defines fundamental breach.
Article 35 establishes conformity requirements.
Article 36 concerns liability for nonconformity existing when risk passes.
Article 38 establishes inspection obligations.
Article 39 establishes notification requirements.
Article 40 limits the seller’s ability to rely on certain notice failures where the statutory conditions are satisfied.
Article 44 provides limited relief in specified notice situations.
Articles 45–52 establish important buyer remedies.
Article 46 addresses performance, replacement, and repair.
Article 48 addresses seller cure rights.
Article 49 governs avoidance by the buyer.
Article 50 establishes price reduction.
Article 51 establishes important rules concerning partial nonconformity.
Articles 74–77 regulate damages and mitigation.
Articles 81–84 address consequences of avoidance and restitution.
Where Turkish domestic sales law applies, Articles 219–231 of the Turkish Code of Obligations No. 6098 establish important rules concerning defective goods.
Article 227 establishes specified buyer remedies.
Article 231 establishes important limitation rules.
Article 23 of the Turkish Commercial Code No. 6102 may establish additional inspection and notification obligations for commercial sales between merchants.
The Turkish Code of Civil Procedure No. 6100 establishes important rules concerning documentary evidence, expert examination, interim judicial protection, and evidence preservation.
Articles 219 and following concern documentary evidence.
Articles 389 and following regulate interim injunctions.
Articles 400–405 regulate evidence preservation.
The Enforcement and Bankruptcy Law No. 2004 establishes relevant enforcement and precautionary attachment mechanisms.
Law No. 5718 establishes important rules concerning international jurisdiction, applicable law, and enforcement of foreign judgments.
The Turkish Penal Code No. 5237 may become relevant where the supplier’s conduct satisfies the elements of fraud, forgery, or another recognized offense.
The central legal distinction is whether the delivered goods failed to satisfy binding technical specifications and whether the nonconformity substantially affected the buyer’s contractual rights.
A minor technical variation does not automatically justify cancellation of the entire contract.
However, serious deviations affecting safety, functionality, compatibility, or commercial suitability may entitle the buyer to significant contractual remedies.
A foreign buyer who receives goods with incorrect technical specifications from Turkey should first identify the governing law.
The buyer should determine whether the CISG applies or whether the parties validly excluded it.
The next question is whether the technical specifications were contractually binding.
The buyer should preserve the supply agreement, purchase order, engineering drawings, approved samples, and relevant communications.
The delivered goods should then be examined through appropriate technical testing.
For example, dimensional measurements, material analysis, performance tests, or safety assessments may be necessary.
The buyer should identify the date of delivery, inspection, discovery, and notification.
Under the CISG, Articles 38 and 39 may be particularly important.
Where Turkish domestic commercial law applies, Article 23 of the Turkish Commercial Code may establish short notification requirements.
The buyer should then identify the appropriate remedy.
Where the nonconformity constitutes a fundamental breach, avoidance or replacement may require consideration.
Where the goods can be corrected, repair or recalibration may be appropriate.
Where the products remain usable but have reduced value, price reduction may require consideration.
The buyer should calculate any additional losses, including testing costs, installation expenses, replacement purchases, project delays, customer penalties, and lost profits.
The applicable damages framework must be examined.
Where the supplier refuses to cooperate, the buyer should assess the dispute resolution clause.
Commercial litigation, arbitration, interim judicial protection, or enforcement proceedings may be available.
Lawyer Fırat Fesih Kaya emphasizes that technical specification disputes require careful distinction between contractual requirements, engineering nonconformity, inspection deadlines, buyer remedies, damages, and cross-border enforcement.
Incorrect technical specifications may affect several legal interests simultaneously.
The contractual issue concerns whether the supplier complied with agreed technical requirements.
The engineering issue concerns the nature and seriousness of the deviation.
The procedural issue concerns inspection and notification deadlines.
The commercial issue concerns rejection, replacement, repair, and price reduction.
The financial issue concerns refunds, lost profits, and additional expenses.
The regulatory issue concerns product safety and conformity requirements.
The international issue concerns governing law, jurisdiction, arbitration, and enforcement.
The criminal issue may arise where the conduct satisfies the elements of a recognized offense.
These matters have different legal requirements.
A foreign buyer cannot automatically reject every shipment because of minor technical differences.
However, a Turkish supplier cannot assume that products are contractually conforming merely because they remain partially functional.
A coordinated legal assessment may therefore be necessary to protect the buyer’s commercial and financial interests.
1. Can a foreign buyer reject goods from Turkey that fail technical specifications?
Potentially. The available remedy depends on the governing law, seriousness of the nonconformity, and compliance with applicable requirements.
2. Does Article 35 of the CISG cover incorrect technical specifications?
Yes. Article 35 establishes important conformity requirements concerning agreed quality, description, and other product characteristics.
3. Can the buyer cancel the contract?
Potentially. Article 49 of the CISG permits avoidance where the relevant requirements, including fundamental breach, are satisfied.
4. Can the buyer demand replacement goods?
Potentially. Article 46(2) of the CISG permits replacement where the statutory requirements are satisfied.
5. Can the buyer demand repair or recalibration?
Potentially. Article 46(3) of the CISG permits repair unless unreasonable in the circumstances.
6. Can the buyer recover an advance payment?
Potentially. Valid avoidance may create restitution rights under Articles 81–84 of the CISG.
7. Can the buyer claim compensation for installation and testing costs?
Potentially. The buyer must establish the relevant loss, causal connection, and applicable legal requirements.
8. Can the buyer recover lost profits?
Potentially. Article 74 of the CISG permits recovery of qualifying lost profits, subject to the statutory requirements.
9. Can a foreign buyer sue the Turkish supplier in Turkey?
Potentially. The competent forum depends on the contract, jurisdiction rules, and any valid arbitration agreement.
10. Can a foreign buyer pursue the dispute without traveling to Turkey?
Yes. A foreign buyer may appoint a Turkish lawyer to assist with commercial proceedings, subject to applicable authorization and procedural requirements.
Protecting international supply contracts, technical investments and buyer rights requires timely and specialized legal assistance.
Foreign companies that receive goods from Turkish suppliers which fail agreed technical specifications may face serious risks involving defective machinery, incompatible components, failed quality tests, rejected shipments, delayed projects, customer complaints, replacement purchases, and substantial financial losses.
Working with a lawyer experienced in Turkish commercial law, international sales contracts, the CISG, technical nonconformity disputes, defective goods litigation, arbitration, and foreign buyer protection can help clarify the applicable legal framework and identify appropriate remedies.
Serving clients throughout Turkey and internationally, Fırat Fesih Kaya Law Office provides professional legal support in technical specification disputes, defective product claims, international supply contract termination, advance payment recovery, compensation litigation, evidence preservation, precautionary attachment, arbitration, and enforcement proceedings against Turkish suppliers.
Lawyer Fırat Fesih Kaya assists foreign buyers, international distributors, importers, manufacturers, wholesalers, retailers, and overseas businesses facing technical nonconformity or contractual nonperformance by Turkish suppliers.
Call Now: +90 312 434 22 22
WhatsApp: +90 532 769 22 22
Email: info@firatfesihkaya.av.tr
Website: https://www.firatfesihkaya.av.tr
Disclaimer: This article is intended for general informational purposes only. To avoid any loss of legal rights, we recommend consulting your lawyer regarding the specific circumstances of your case.